41-47 Raadhuislaan
Last modified on: May 29, 2026
A new health center and 44 housing units will be built at Raadhuislaan 41-47. There is a great need for housing and for future-proof accommodations for general practitioners and other healthcare providers. The health center will house various healthcare providers and a pharmacy. Of the 44 housing units, 25% will be social housing and 10% will be mid-range rental units.
The project initiator, Niersman Projectontwikkeling B.V., conducted a design study in consultation with the municipality to explore the integration of a health center and apartments. Local residents were also involved in this process. On September 26, 2024, the city council adopted the Implementation Framework for the project. Among other things, it specifies the building’s permitted size and height, parking arrangements, and guidelines for green spaces. The developer is now further refining the design.

Current Status
The Implementation Framework was adopted by the city council on September 26, 2024. In December 2024, the preliminary agreement with the municipality was signed. Work is currently underway to further develop the design. To that end, the necessary studies are also being conducted. The permitting process is expected to begin in Q3 2025, and if all goes well, construction can begin in 2026.
Planning
Completed: 2018
Land for Sale
Completed: November 2022
Residents' Meeting.
Completed: February 2023
Residents' meeting on design options.
Completed: May 2023
Introductory statement to the city council.
Completed: April 2024
Residents' meeting on the preferred option.
Completed: September 2024
Implementation framework adopted by the city council.
Completed: December 2024
A preliminary agreement was signed with the project sponsor.
Currently in progress: 2025 –2026
Develop the preliminary design and complete the permitting process.
Currently in progress: Q2 2026
Received a permit for a zoning plan amendment.
Still to be done: Q3 2026
Submission of a permit application for a technical building permit (expected).
Still to be done: Q1 2027
Environmental permit is final (expected).
Still to be done: Q2 2027
Sales start (expected).
Still to be done: Q4 2027
Start of demolition (expected).
Still to be done: Q1 2028
Start of construction (expected).
Participation
The Municipality of Voorschoten would like to hear from stakeholders about what they consider important for the site. During the design study, three community meetings were held to gather input from local residents. This input has been incorporated into the design to the greatest extent possible. The meeting reports can be found at the bottom of this page.
Would you like to learn more about the initiative, or would you like to sign up to receive updates in the future? If so, please send an email toraadhuislaan@niersman.com.

Contact and More Information
Do you have any questions or comments about the construction project? If so, please contact Niersman atraadhuislaan@niersman.com. Do you have a question for the municipality? If so, please send an email toraadhuislaan@voorschoten.nl.