Request transportation capacity in advance

The “Early Application for Transportation Capacity” program allows the municipality to apply for transportation capacity early in the planning process. The program is intended for projects involving residential construction, educational facilities, and collective housing.

The first coordinated application round runs from October 1 through October 23, 2026. Projects could be submitted for this round from August 31 through September 15, 2026. New projects may also be submitted after that date. For applications submitted after October 23, the standard procedure applies.

What are the rules?

In many places in the Netherlands, there is not enough capacity on the power grid. We call this grid congestion. As a result, new projects cannot always be connected immediately. This can cause delays in housing construction projects and educational facility projects.

Under the “Early Application for Transmission Capacity” program, the municipality can apply for transmission capacity and public priority on behalf of a project initiator at an early stage. Transmission capacity refers to the available space on the electricity grid for drawing or feeding electricity back into the grid.

This regulation allows municipalities to bring projects to the attention of the grid operator at an earlier stage. 

Liander, the grid operator, is responsible for the gas and electricity grid in the municipality of Voorschoten.

On September 22, 2026, the municipality of Voorschoten published a priority list for projects that will be given priority by grid operator Liander. View the priority list below.

The order of events has been announced

Developers who wanted their projects to be considered for the waiting list had until September 15, 2026, to submit their projects to the municipality. The municipality has reviewed the submitted projects.

The priority list has been drawn up in accordance with the established policy guidelines for requesting priority for transportation capacity. In doing so, the municipality considers, among other things:

  • The planned start of construction
  • How far along the project is in its preparation
  • The social significance of the project
  • The expected completion date

View the order list

The table below shows the data on which the ranking list is based.

Order

Project

Developing Party

Phase

Is a lottery needed?

11608 - Starrenburg III, VoorschotenThe Development CouncilPhase 1: VlietoeversNo
2Starrenburg III, VoorschotenNiersman Project Development, LLCPhase 2: Strandwal, Part 2No
3Starrenburg III, Voorschoten Niersman Project Development, LLCPhase 1: Strandwal, Part 1No
4Jan WagtendonkstraatRijnhart HousingPhase 1No
5NoortveerMunicipality of VoorschotenPhase 1No
61608 Starrenburg III - VoorschotenThe Development CouncilPhase 2: South IslandNo
7Oude StationslaantjeRijnhart HousingPhase 2No
8Oude StationslaantjeRijnhart HousingPhase 1No
91608 - Starrenburg III, VoorschotenThe Development CouncilPhase 3: Strandwal No
10Church of the Mother of GodNiersman Project Development, LLCPhase 1No
11PapelaanNiersman Project Development, LLCPhase 1No

Project

Step 1: Start construction

Step 2: Project Readiness (score 1 through 6)

Step 3: Social Impact (score 0–3)

Step 4: Expected Completion Date

1608 - Starrenburg III, VoorschotenApril 1, 202710October 17, 2028
Starrenburg III, VoorschotenApril 1, 202710March 1, 2030
Starrenburg III, Voorschoten April 1, 202741March 1, 2028
Jan WagtendonkstraatOctober 1, 202741May 1, 2028
NoortveerJanuary 1, 202851July 1, 2029
1608 Starrenburg III - VoorschotenAugust 15, 202841June 1, 2030
Oude StationslaantjeJuly 1, 202942December 1, 2029
Oude StationslaantjeJuly 1, 202942June 15, 2031
1608 - Starrenburg III, VoorschotenApril 23, 203040May 1, 2031
Church of the Mother of GodJuly 1, 203060July 1, 2032
PapelaanJanuary 1, 203161January 1, 2033

To which projects does the program apply?

The "Early Application for Transport Capacity" program is intended only for:

  • Housing Development Projects
  • Educational Facility Projects
  • Projects for communal living arrangements

The project must comply with the prioritization framework established by the Netherlands Authority for Consumers and Markt s (ACM). The project must also be completed within 10 years.

The municipality cannot assign priority to business projects.

What are the benefits of participating?

Projects with a social priority are moved up on the grid operator’s waiting list. This allows the grid operator to include the project in its capacity planning sooner.

Participation does not guarantee:

  • A connection to the power grid
  • Available transport capacity
  • A connection on a specific date

The grid operator Liander determines when capacity is available on the power grid.

How does it work?

Below is a step-by-step guide to how the program works. Please read the steps and Requirements carefully so you know what to do.

Step 1: Register your project

Project organizers could submit their projects to the municipality from August 31 through September 15, 2026.

The registration period has now closed. New projects can no longer be added to the waiting list.

Step 2: Submit a project proposal

A complete project file must be submitted for each project. This file contains the most important information about the project.

Step 3: Review by the municipality

The municipality evaluates all submitted projects in accordance with established policy guidelines.

View the policy guidelines for requesting priority for transportation capacity on the website lokaleregelgeving.overheid.nl.

Step 4: Finalizing and Publishing the Ranking List

On September 22, 2026, the municipality adopted and published the priority list. This list determines the order in which projects are submitted to the grid operator.

Step 5: Appeal Period

Interested parties may respond to the ranking list within 10 days.

After this period, the municipality will review the responses. The municipality will then determine the final order.

Step 6: Registration with the grid operator

The municipality submits the projects to the grid operator in the established order. Liander then assesses how much capacity is available.

Important Dates

Developers had until Tuesday, September 15, 2026, to submit their projects. Therefore, it is no longer possible to add new projects to the waiting list.

See the important dates below.

Activity

Date

Registration Period OpensAugust 31, 2026
Registration Period EndsSeptember 15, 2026
Adoption of the Order of Precedence ListSeptember 22, 2026
Objection Period10 days after the ranking list is finalized
Submission to the grid operatorOctober 1–23

Time blocks based on the year of initial construction

The municipality processes applications in batches. In doing so, we consider the project’s planned start year for construction. The planned start year for construction determines when a project is submitted.

The grid operator then assesses how much capacity is available and how it is allocated among the registered projects.

Application Date

Projects with a start year

As of October 1, 2026, at 9:00 a.m.Construction to begin through 2028
As of October 6, 2026, at 9:00 a.m.Construction to begin through 2029
As of October 8, 2026, at 9:00 a.m.Construction to Begin Through 2030
As of October 12, 2026, at 9:00 a.m.Construction to Begin Through 2031
As of October 14, 2026, at 9:00 a.m.Construction to begin through 2032
As of October 16, 2026, at 9:00 a.m.Construction to begin through 2033
As of October 20, 2026, at 9:00 a.m.Construction to Begin Through 2034
As of October 22, 2026, at 9:00 a.m.Construction to begin through 2035

What information do you need to provide?

A project proposal is required to evaluate an application. Depending on the project, the municipality may request:

  • A description of the project;
  • The project schedule;
  • The number of housing units or school seats;
  • A justification of the planning status;
  • A prior agreement or other supporting documents;
  • Information about the required electrical connection.

The policy guidelines specify exactly what information is required. View the policy guidelines for applying for priority for transportation capacity on the website lokaleregelgeving.overheid.nl.

How does the municipality determine the order?

The municipality draws up a priority list based on the policy guidelines at . Among other things, the following factors are taken into account:

  • The planned start date for construction
  • How far along the project is in its preparation
  • The social significance of the project
  • The expected completion date

If projects tie in all categories, the municipality may conduct an additional evaluation or hold a lottery. This is done in accordance with the policy guidelines.

This approach ensures that projects are evaluated in a transparent and objective manner.

Frequently Asked Questions and Answers

Below is a list of frequently asked questions and answers about the program.

Is your question not listed here? If so, you can contact the municipality by email at: duurzaam@voorschoten.nl.
 

Will I automatically be connected?

No. A spot on the waiting list and social priority do not guarantee transportation capacity or an electricity connection.

Can I still submit an application after October?

Yes. You can still submit an application after October. Please note: Your application will then be placed on the waiting list behind the applications submitted earlier.

Can I submit a business project?

No. This program is intended only for projects involving residential construction, educational facilities, and collective housing that meet the “ Requirements ” criteria of the ACM prioritization framework.

How much does it cost to submit a project?

Submitting a project to the municipality is free.

The grid operator may, however, charge certain fees, such as an advance payment or connection fees. These costs are the responsibility of the project initiator.

Why does the municipality determine an order?

Under the ACM prioritization framework, the municipality has been tasked with coordinating applications for housing and education. For this reason, the municipality is drawing up an objective and transparent priority list.

Questions or would you like more information?

Do you have any questions about this program, or would you like to know if your project is eligible? Please contact the municipality by email at duurzaam@voorschoten.nl.